Quiz-summary
0 of 8 questions completed
Questions:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
Information
Journeyman HVAC IMC Online Test 8
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading...
You must sign in or sign up to start the quiz.
You have to finish following quiz, to start this quiz:
Results
0 of 8 questions answered correctly
Your time:
Time has elapsed
You have reached 0 of 0 points, (0)
Average score |
|
Your score |
|
Categories
- Not categorized 0%
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- Answered
- Review
-
Question 1 of 8
1. Question
1 pointsWhich of the following flammable liquid having a flash point below 73°F (23°C) and a boiling point below 100°F (38°C)
Correct
Incorrect
-
Question 2 of 8
2. Question
1 pointsIntake openings shall be located not less than 3 feet below contaminant sources where such sources are located within _____ of the opening:
Correct
Please Refer: IMC Code 401.4.3
Incorrect
Please Refer: IMC Code 401.4.3
-
Question 3 of 8
3. Question
1 pointsFerrous fan blades shall only be used for fans located within the ductwork and through which hazardous materials are exhausted.
Correct
Please Refer: IMC Code 502.9.4
Incorrect
Please Refer: IMC Code 502.9.4
-
Question 4 of 8
4. Question
1 pointsAs per Department of Transportation (DOT) specification cylinders with a maximum water capacity of _____ shall be used for completely self-contained hand torches and similar applications
Correct
Please Refer: IMC Code 502.9.10.1
Incorrect
Please Refer: IMC Code 502.9.10.1
-
Question 5 of 8
5. Question
1 pointsDucts shall be supported with approved hangers at intervals not exceeding _____ :
Correct
Please Refer: IMC Code 603.10
Incorrect
Please Refer: IMC Code 603.10
-
Question 6 of 8
6. Question
1 pointsSmoke detectors shall be installed in return air systems with a design capacity greater than _______ , in the return air duct or plenum upstream of any filters:
Correct
Please Refer: IMC Code 606.2.1
Incorrect
Please Refer: IMC Code 606.2.1
-
Question 7 of 8
7. Question
1 pointsWhere the vent vertical termination is located below an adjacent roof structure, the termination point of mechanical draft system shall be located at least _____ from such structure:
Correct
Please Refer: IMC Code 804.3.5.3
Incorrect
Please Refer: IMC Code 804.3.5.3
-
Question 8 of 8
8. Question
1 pointsVenting systems shall be designed and constructed so as to develop a ______ flow adequate to convey all combustion products to the outside atmosphere:
Correct
Please Refer: IMC Code 801.4
Incorrect
Please Refer: IMC Code 801.4